North American Material association: The challenge

Data center growth creates large volumes of end‑of‑life copper
FEV was asked to analyze recycling pathways to identify levers to improve copper preservation and circularity​

FEV e+r: Our involvement and solution

Defined end of life scope for copper bearing data center infrastructure, covering power cables, busbars, switchgear, cooling systems, and mixed IT and electrical equipment

Structured assessment of data center change events impacting copper recovery, including technology refresh, capacity retrofit, decommissioning scenarios

Qualitative evaluation of removal practices comparing intact extraction, selective removal, and bulk demolition approaches and their impact on copper value

End to end mapping of the copper recovery value chain, identifying key actors, material routing decisions, and points where copper value is preserved vs. diluted

Development of two representative end of life pathway archetypes to illustrate recovery risks: clean and segregated recovery vs. mixed demolitionscrap outcomes

Get in touch with us through our Contact form

Ähnliche Beiträge

  • From Water Quality to Cell Integrity: A Comprehensive PEM Stack Forensics Study

    An industrial customer sought an independent second opinion on purchased and stored PEM electrolyzer stacks prior to installation in its electrolysis systems...

  • FEV supports BESS investment decisions through BESS Redflag Report and asset simulation

    The challenge Investors and asset owners need to understand both the current condition and the future potential of operating battery energy storage systems. The challenge is to identify technical risks, assess remaining useful life, and evaluate…

  • FEV and Regout Group Collaborate on Smart Energy Management through PV–BESS Integration

    The Regout Group, a leading industrial manufacturer in Maastricht, aims to enhance sustainability and reduce energy costs. With rising electricity prices and the need for greener operations, the challenge was to identify an optimal mix of renewable energy generation and…