Uniper SE: The challenge

FEV was asked to support the development of a Mobile Fast Charger (MFC) from ideation to Proof of Concept (PoC)

FEV e+r: Our involvement and solution

Derivation of business model ideas for applications of MFCs and conduction of consumer survey to confirm analysis

Leverage of partner network to identify and select state-of-the-art components, incl. battery unit & power electronics

Installation of microgrid to allow vehicle charging without grid connection

Development of Operational Management System for remote condition monitoring & organization of operations

Integration of high-performance cooling system with dedicated cooling strategy

Assembly & functional testing of 2 PoCs with:

  • 150 kWh usable energy capacity
  • 2 x 75 kW charging power (CCS 2.0 & CHAdeMO)

CE certification based on Hazard and Risk Analysis (HARA)

 

Get in touch with us through our Contact form

Ähnliche Beiträge

  • From Water Quality to Cell Integrity: A Comprehensive PEM Stack Forensics Study

    An industrial customer sought an independent second opinion on purchased and stored PEM electrolyzer stacks prior to installation in its electrolysis systems...

  • Copper end‑of‑life recovery pathways in data center infrastructure

    Data center growth creates large volumes of end‑of‑life copper FEV was asked to analyze recycling pathways to identify levers to improve copper preservation and circularity…

  • FEV supports BESS investment decisions through BESS Redflag Report and asset simulation

    The challenge Investors and asset owners need to understand both the current condition and the future potential of operating battery energy storage systems. The challenge is to identify technical risks, assess remaining useful life, and evaluate…